1928
April
The first DG4 waggon (No. 7277)
was sold.
1930
May
Britains first ready-mix concrete body was supplied fitted to DG6 No 8213.
1930
July
The first DG Tractor (N0. 8216) was brought into practical service using the
DG waggon engine. Only nine of these were built of which four have survived
in preservation.
1929
August
The worlds first ever rigid eight-wheeler Sentinel DG8 was introduced (No
8002) of which only eight were built still with solid rubber tyres.
1930
October
First railcar with two six-cylinder engines supplied to LNER
(No 7824) Phenomena.
1931 January
Shaft Drive Double Geared (SDDG4) waggon was produced
(No. 8448) with pneumatic tyres. It had an all new four-cylinder single-acting
engine. This waggon fortunately still survives
in preservation.
1931
June
New lightweight DG6 on pneumatic tyres introduced (No 8554) in response to
the new Road traffic Regulations which allowed a max speed of 20 mph. Pneumatic
tyred DG4’s and trailers were also available